Capabilities

Quality & traceability

We agree the records needed to identify and maintain each delivered hardware platform: mechanical parts, base and arm models, firmware, interface revision, calibration and acceptance results. Your scheduling software remains under your team’s release control.

Records linked to each unit

Start from the service question: if a unit needs investigation, what information must be recoverable? A useful identification scheme relates the physical unit to its drawing revision, bill of materials and approved configuration. Where the failure risk warrants it, the record also identifies component lots or individual serial numbers.

A label alone is not traceability. Decide which record is authoritative, how a replacement component is recorded and how the OEM receives the information after shipment.

RecordContent to agreeQuestion it should answer
Unit identityUnique unit or assembly ID and product configurationWhich product was delivered?
Component historyRequired serial or lot references and approved substitutionsWhich components were installed?
Assembly evidenceInstruction revision, required checks and sign-offWhich build instructions were followed?
Acceptance evidenceTest plan revision, conditions, results and dispositionWhy was this unit accepted?
Change historyChange approval and first affected unit or batchWhen did the configuration change?

Hardware configuration record

Before the build, we agree the configuration fields and retention requirements with your team. The record connects the delivered unit to its mechanical parts, selected base and arm, firmware, calibration and acceptance results.

RecordInformation includedUse during service
Unit identityUnit serial number or assembly ID and product configuration.Identify the hardware being inspected or maintained.
As-built configurationReleased BOM and drawing revisions; required component models, lot references and serial numbers.Check which parts were installed and which replacements are approved.
Assembly and calibrationApplicable work instructions, inspection entries, adjustment results and calibration settings.Restore the assembly to its recorded setup after service.
Firmware and interfacesBase and arm firmware, relevant parameters and platform interface revision.Check compatibility before a controller, firmware or software interface changes.
Acceptance resultsTest plan revision, tested configuration, results and disposition of open items.Identify the checks completed before hardware handover.
Engineering changesApproved change, affected parts and first applicable unit or batch.Determine whether a change applies to the unit being serviced.

We record approved deviations against the affected unit. After a repair or component replacement, the service record needs to identify the new configuration and any calibration or tests repeated.

Incoming inspection

Use the bill of materials and risk assessment to choose which incoming attributes require inspection. A machined interface may need dimensional checks; a purchased controller may need model, revision and condition verification. Agree sampling or full inspection where appropriate rather than writing “all components checked” without a method.

Define what happens to a nonconforming part: identification, segregation, disposition and reinspection after correction. Substitutions should follow the agreed approval process, especially for safety-related parts or parts that affect validation.

Assembly records

The exact fields should reflect the product. Excessive paperwork can obscure the few decisions needed to understand a build; missing configuration information can make a detailed test record impossible to interpret.

  • Drawing and instruction revision at the time of build.
  • Assembly-critical dimensions and adjustment results.
  • Required electrical identification, routing and connection checks.
  • Configuration of firmware or software supplied for the product.
  • Nonconformities, rework authorization and the checks after rework.

Engineering changes

Agree authority for deviations, concessions and permanent design changes separately. An assembler should not have to infer whether an email, sketch or old drawing remains valid. The change record should identify any effect on existing stock and service spares.

Transfer sequence
  1. OEM approves the change
  2. Affected documents are released
  3. Stock and work in progress are reviewed
  4. First affected unit is identified
  5. Required checks are performed
  6. Updated records accompany release

How do a deviation, an engineering change and a repair differ?

Record typePurposeControl to agree
Deviation or concessionDocument an authorized exception for a defined part, unit or batch.Scope, reason, assessment, approver, expiration or quantity limit, and any additional checks.
Engineering changeRevise the approved design, material, process or test baseline.New revision, impact review, implementation point and treatment of stock or work in progress.
Service repairRecord work performed on an identified unit after release.Removed and installed parts, resulting configuration and the checks needed before return to service.

Do not silently rewrite the original build history after repair. Link the service record to the unit and preserve the sequence of configurations. The depth of retention, access and approval should be agreed with the OEM for the product and its intended use.

Reviewing the record package with us

Before assembly, we review the traveler, inspection sheet, test report and configuration record with your team. We agree the required fields, responsible reviewers, retention period and delivery format for your order.

  • The link between a unit ID, its build configuration and acceptance results.
  • The responsible person and acceptance authority for each required check.
  • Record retention, customer access and delivery format.
  • Rules for inspection equipment suitability and calibration where measurement accuracy matters.
  • How corrections are recorded without losing the original result.

Common questions

Is serial-number tracking enough?

No. The identifier must connect to useful configuration and acceptance information. Define the required relationships in the quality plan.

How should an OEM verify the scope of a quality certificate?

We review any required certification with you against the actual legal entity, manufacturing location and contracted work. The certificate’s scope and validity must cover the work for which it is being requested.

Can the OEM specify its own forms?

Include the forms and instructions in the manufacturing review. Agreement is needed on fields, responsibilities, retention and delivery.

Should every component be serialized?

Not necessarily. Choose unit, lot or component-level identification according to product risk, contractual requirements and service needs.

Can customer records be used as public evidence?

We do not share customer records without permission. For a project review, we agree a record format or a permitted anonymized example.

Record the platform interface configuration

For an integrated platform, agree records for the body and machined part revisions, base and arm models, relevant firmware and parameter versions, external interface definition and calibration results. Link approved changes to the affected build.

Customer scheduling software has its own release history. Where it is used during acceptance, record the tested customer software version alongside the platform configuration.

Discuss your hardware requirements

Send us your carrier dimensions, workstation layout, software interface requirements and expected quantities.

Discuss an OEM Project